contributed…..WisDOT Staff (w/ SCS Engineers support): Construction Project Engineer: Dale Merten, Field Office Phone #: (920) 948-0297; e-mail: Dale.Merten@dot.wi.gov Field Office Location: Lycon Ready Mix Plant, 421 Maughs St, Mauston

Project Description:  The $2.2 million project involves reconstruction of South Union Street and ultimate redesignation as STH 58/82. A single-lane roundabout will also be constructed at the intersection of Grayside and Division Streets. And finally, the current STH 58/82 roadway along Division Street will be milled and resurfaced with new asphalt. Work is scheduled to be completed by early November, 2013.

The work includes installation of new utilities, storm sewer, concrete pavement, sidewalks, street lighting and signs. The roadway curve on the southeast corner of the park will be enlarged to better accommodate trucks, and the curbs along South Union will be narrowed to accommodate a wider grass boulevard.

Proposed Schedule:  The staging given below is tentative and subject to change but generally lists the anticipated timeframe for some of the major activities as currently proposed.

June 3, 2013 – mid October, 2013 (Stage 1A – 3)

Close East Grayside & South Union Street to do underground work & reconstruct roadway.

June 7, 2013 – mid October, 2013 (Stage 1A – 3)

Close West Grayside (& utilize detour route) to begin construction of the new roundabout.

week of June 10, 2013 – week of June 24, 2013 (Stage 1A)

Division Street traffic will be shifted to the west side of the roadway near the new roundabout location to place temporary asphalt widening along the east side of the roadway.

week of June 24, 2013 – week of July 15, 2013 (Stage 1B)
Northbound Division Street will be shifted to the east side of the roadway and new construction of the roadway and roundabout will occur between the split traffic lanes.

week of July 15, 2013 – week of August 19, 2013 (Stage 1C)

Division Street traffic will be shifted to the east side of the roadway near the new roundabout location to complete construction of the west side of the roadway and roundabout.

week of August 19, 2013 – week of September 9, 2013 (Stage 2)

Both lanes of Division Street will be shifted slightly to the west, south of the roundabout to construct the new pavement along the east side in that area and to the final lanes through the roundabout.

week of September 9, 2013 – week of October 14, 2013 (Stage 3)

Both lanes of Division Street will be located virtually in the final lane locations while final completion of the roundabout area is done.

week of October 14, 2013 – November 1, 2013 (Stage 4)

West and East Grayside will be re-opened. Division Street North will then be closed for a short time to mill off and re-pave the top 2″ of asphaltic surface.

The contractors & WisDOT wish to THANK YOU for your patience during this project.  Mauston D.O.T. Staging