November 8th Update

We are winding down on both projects but there are still many smaller areas that need to be completed that will require several, short term traffic changes.  A lot of finishing work such as signing, pavement markings & electrical will require short term traffic pattern shifts to complete. Again both projects still require a lot of miscellaneous work to complete which may require short adjustments to traffic patterns so I would like to remind everyone to please be attentive while driving through the work zone.  We are hoping to be completely done with the work by mid-November.

If anyone has any questions or concerns you may contact me (Dale Merten) at the field office at (715) 797-2428.